Creating a good working relationship with a group willing to undertake some pretty immense tasks is imperative. At Rufford we have a few groups who come in and one of particular note is North Notts College. We have tailored certain practical tasks to match their syllabus. Previously they have ticked off clearing a waterway by digging silt out so there is better waterflow into the Wetland Conservation Area. So when their syllabus stated they needed to fix something that was broken a 20+ year old bridge seemed a perfect match. After running through what needed doing and pushing an 'artists' impression of the new bridge in their faces (see below) we began work.
First job was to remove vegetation and hazards around the bridge to create a good work area, this including going in the water pulling vegetation out, coppicing willow and slashing nettles.
|
Before |
|
After vegetation clearance |
|
After bridge removal |
After the work area was made safe two older sleepers were put in as a temporary bridge to cross over to the island with tools. Then the hard work began, bank re-profiling, post hole digging, sawing all wood to length and much more. The pictures don't do the final bridge justice, it looks great and we are very thankful to groups such as North Notts College for their very hard work. Final bridge below.
|
Halfway |
|
Finished!! |
WELL DONE NORTH NOTTS COLLEGE!!!
No comments:
Post a Comment